Settlement of land records in districts Dir Lower, Dir Upper and Tehsil Kalam, Swat

Project Title (As per ADP):Settlement of land records in districts Dir Lower, Dir Upper and Tehsil Kalam, Swat

ADP No:  190183

      Approval Date: 22nd, December, 2020

      Approved Cost: 1931.089 M

      1st Revision Date: 10th, October, 2025

      1st Revised Cost:  2483.762 M

      Project Closing date: 30th, June, 2027

DistrictArea (Sq. km)PopulationNo. of HHNo. of Mouzas
Dir Lower1,5971,650,183202,836 216
Dir Upper3,7521,083,566149,536121
Kalam2,10384,4849,81017
Total7,4522,818,233362,182354

Total Project Cost : 2483.762 Million PKR

DetailsDemandAllocationReleaseExpenditure
ADP Allocation for 2021-22253.5120.051120.051119.868
ADP Allocation for 2022-23239.5193.263193.263192.699
ADP Allocation for 2023-24289.716195.454195.454195.408
ADP Allocation for 2024-25645251.920251.920251.911
ADP Allocation for 2025-26527230.032217.422217.422
ADP Allocation for 2026-27760.515500
TOTAL2,715.2161145.72978.11977.308

REVENUE PHYSICAL PROGRESS ACHIEVED

DistrictNo. of MouzaPublic AwarenessThak Bast (Total Area)Shajra e Nasab By Revenue Staff Shajra e Nasab In LRMIS
Dir Lower216100%100%344,084 (100%)344,084 (100%)
Dir Upper121100%100%173,587 (80%)155,973 (90%)
Kalam17100%100%16,598 (25%)11,551 (69.5%)
Total354100%100%534,269 (68.3%)511,608 (86.5%)

FIELD PARCEL MEASUREMENT PROGRESS (TEHSIL-WISE)

TehsilTotal Active MouzasCompleted MouzasIn-Progress Mouzas
Adenzai4717 (36%)6
Balambat395 (13%)3
Timergara354 (11%)1
Lal Qilla365 (14%)
Munda181 (6%)
Samar Bagh292
Kalam171 (6%)1
Total22133 (15%)13

Project Brief:

The Project envisions establishment of accurate, transparent and secure land records based on Geographic Information System (GIS) for the Districts of Dir Lower, Dir Upper and Tehsil Kalam (Swat) of Khyber Pakhtunkhwa.The project will be started in all seven subdivisions of Dir Lower and Dir Upper and Tehsil Kalam at the same time. Details of the project area is given below: